Below is a step by step guide showing a typical lagoon installation.

Key Facts

Location: Woodside, Jersey

Material Use: 1.00mm Firestone EPDM

Size: 2000sq. meters

Time to install: 4 Days

Stage1-Ground-Preparation-Reservoir

Stage 1: Ground Preparation

Stage 1: Ground Preparation

Prior to the liner installation the lagoon is excavated to the required dimensions. During this stage an anchor trench is dug. This will be used to hold the edges of the liner in place

 

 

 

 

 

Stage2-Base-Matting-Reservoir

Stage 2: Base Matting Installation

Stage 2: Base Matting Installation

Protective matting is then laid across the base to protect the liner from sharp objects.

 

 

 

 

 

Stage3-Base-Liner-Reservoir

Stage 3: Liner Installation

Stage 3: Liner Installation

Once the matting has been laid the liner is installed over the top. This overflows into the trench where it will be anchored securely

 

 

 

 

 

Stage4-Seam-Joining-Reservoir

Stage 4: Seam Joining

Stage 4: Seam Joining

During the installation any seams between rolls of liner are securely joined using specialist tapes and adhesives.

 

 

 

 

 

Stage5-Installation-Complete-Reservoir

Stage 5: Installation Complete

Stage 5: Installation Complete

The irrigation lagoon liner installation is now complete after just 4 days, leaving a high quality, durable and highly functional irrigation lagoon.

 

 

 

 

 

Stage6-Lagoon-In-Use-Reservoir

Stage 6: Lagoon in use

Stage 6: Lagoon in Use

Just a short while later the lagoon is in full operational use, ensuring a reliable supply of water to the customer.